Generally when the complete stone crushing plant has been set up, it needs the commissioning process. And the commissioning process consists of no-loading commissioning and loading commissioning.
Here are the tips for no-loading commissioning as follows:
1. It should last for two consecutive hours;
2. During the commissioning, the temperature of the bearings should be lower than 30 degrees;
3. Make sure that all the firmware are fastened well;
4. Make sure that the fly wheel and the belt pulley run well;
5. Shut down the machine if there is abnormal noise in it.
The loading commissioning should proceed after a successful no-loading commissioning.
Our company is a professional and reliable ore processing machine manufacturer. We also supply stone crusher, mobile crusher etc. More information about our machine, please feel free to contact with us by phone or e-mail at any time!